Srondoire Wind Farm

  • Anchor cage on blinding

    4Anchor cage was precisely leveled to ensure correct tolerances were adhered to for the tower sections.

  • Reinforcement for base

    40T of steel reinforcement for each base, built upon 100mm blinding with ducts running beneath.

  • 365m³ Concrete Pour

    With 8 turnaround lorries and on site batching plant, duty standby concrete pumps pours still took 12 hours

  • Tower and blade lifting

    Ainscough undertook the lifting from the tested crane pads as set out by us to the specified dimensions.